● Paving/Main Street Sidewalk Construction Update 07/30/20

July 31, 2020

DATE: Thursday, 7/30/20

PROJECT TYPE: Roadway

LOCATION: Beginning on VT Route 116 in Bristol near the intersection of Airport Road at mile marker 6.006 then running north for 1.230 miles and ending at Class I/State Highway limit at mile marker 7.263 in Bristol.

PLANNED CONSTRUCTION ACTIVITIES: (Please be advised that the construction schedule is subject to change)

  • Week of 8/3: Crews will continue to work on adjusting storm drain elevations Monday through Wednesday next week. This work will be performed during daytime work hours. One-way alternating traffic may be required in these areas depending on the location of the structure(s).
  • On Monday, 8/3 a crew is scheduled to install the bollards around the two hydrants located in the downtown/business area (near Vermont Tree Goods and in front of Cubber’s). This will be done early in the day.
  • Night Work: Scheduled for Monday, 8/3 through Thursday, 8/6 from approximately 7:00 PM-11:00 PM
  • Crews will begin prep work for the stamped concrete areas on the north sidewalk on Monday night. Beginning Tuesday night and continuing through Thursday, the cement for the stamped concrete will be placed in prepped areas.

COMPLETED WORK:

  • The concrete step at Kimball’s store has been poured.
  • The concrete step at Wokky’s and in front of the entrances at the attorney’s office have been poured.
  • All remaining sidewalk ramps throughout the project have been poured.

TRAFFIC IMPACTS:

  • Expect one-way alternating traffic in the vicinity of crews adjusting structures. Brief delays should be expected.

As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to certain safety restrictions.

CONTACT INFORMATION:

Name – Natalie Boyle
Phone – 802-855-3893
Email – nboyle@eivtech.com