● Paving/Main Street Sidewalk Construction Update 10/15/20

October 15, 2020

DATE: Thursday, 10/15/20

PROJECT TYPE: Roadway

LOCATION: Beginning on VT Route 116 in Bristol near the intersection of Airport Road at mile marker 6.006 then running north for 1.230 miles and ending at Class I/State Highway limit at mile marker 7.263 in Bristol.

PLANNED CONSTRUCTION ACTIVITIES: (Please be advised that the construction schedule is subject to change)

  • Paving of driveway aprons throughout the project will continue next week, weather permitting.
  • Shoulder back-up will take place throughout the project, which entails placing aggregate material along the side of the road to fill in any low shoulder areas.
  • Crews will topsoil, seed, and mulch in areas as needed, and will begin working on miscellaneous work items and details that remain to be completed prior to the project coming to a close.

TRAFFIC IMPACTS:

  • Expect one-way alternating traffic in the vicinity of paving and shoulder operations. Minor delays should be expected.

As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to certain safety restrictions.

CONTACT INFORMATION:

Name – Natalie Boyle
Phone – 802-855-3893
Email – nboyle@eivtech.com

#bristolsidewalkproject2020