● Paving/Main Street Sidewalk Construction Update 10/22/20

October 24, 2020

DATE: Thursday, 10/22/20

PROJECT TYPE: Roadway

LOCATION: Beginning on VT Route 116 in Bristol near the intersection of Airport Road at mile marker 6.006 then running north for 1.230 miles and ending at Class I/State Highway limit at mile marker 7.263 in Bristol.

PLANNED CONSTRUCTION ACTIVITIES: (Please be advised that the construction schedule is subject to change)

  • Paving of driveway aprons is scheduled for completion next week, weather permitting. Inclement weather has been pushing the paving schedule back.
  • Top soiling, seeding and mulching is nearly complete. Motorists should refrain from parking or driving on these areas, particularly while turf is being established.
  • Once driveway aprons are completed, crews will begin to work on miscellaneous items and details that remain to be completed prior to the project coming to a close.
  • This will be the last regular construction update for this project. The contractor will continue with miscellaneous final inspection items over the course of the next few weeks, but these activities will not have a significant impact on the flow of traffic.
  • Thank you for your patience throughout this construction project.

TRAFFIC IMPACTS:

  • No significant traffic impacts are expected throughout the week of 10/26/20.

As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to certain safety restrictions.