Paving/Main Street Sidewalk Construction Update 06/4/20

June 5, 2020

DATE: Thursday, 6/4/20

PROJECT TYPE: Roadway

LOCATION: Beginning on VT Route 116 in Bristol near the intersection of Airport Road at mile marker 6.006 then running north for 1.230 miles and ending at Class I/State Highway limit at mile marker 7.263 in Bristol.

PLANNED CONSTRUCTION ACTIVITIES:

  • Day work and night work will continue next week on the project. Allowable night work hours are 7:00 PM to 6:00 AM per the contract for this project. Night work typically begins Sunday night through Thursday night (ending Friday morning).
  • Next weeknight crews will continue installing curb and prepping sidewalk areas.
  • Light towers and construction equipment will be in use. Residents should expect construction noise throughout the night.
  • Berm removal is scheduled to begin next week throughout the east end of the project. When all berm areas on the eastern end have been addressed, crews will move to the western portion of the project. Please expect alternating one-way traffic in the vicinity of berm removal operations.

TRAFFIC IMPACTS:

Expect alternating one-way traffic in the area of berm removal. Delays should be expected.

As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to certain safety restrictions.

CONTACT INFORMATION:

Name – Natalie Boyle
Phone – 802-855-3893
Email – nboyle@eivtech.com

#bristolsidewalkproject2020

Categories: News