Village-Wide Water Line Replacement Initiative

Village-Wide Water Line Replacement

What

New water mains replacing 1905 cast iron

How

Four phases one done, one under way

Now

Phase 2 Bristol West, through Nov 2027

Next

Phase 3 Bristol East, 2028

Funding

50% forgiven State loans

Questions

Town Administrator (802) 453-2410 ext. 1

Why Bristol is replacing its water mains

More than half of Bristol’s water system went in around 1905. It is unlined cast iron pipe, well past its expected life. The old pipe leaks far more water than is typical, which raises operating costs and leads to emergency repairs, service interruptions and patched pavement. It also limits the water available to fight fires and raises the risk of contamination.

A 2021 engineering study of the whole system made replacing the 1905 pipe a top priority. The full job, then estimated at $12 to $13 million, was too large for the State to finance at once. In 2022 the Selectboard, acting as the Water Commission, split it into four phases.

Map of the Bristol village water system. Phase 3 streets are red, Phase 2 streets are blue and Phase 4 is green.
VTM Engineering phase map, September 2024. Preliminary, not for construction. Click to enlarge.

▬ Phase 2, Bristol West ▬ Phase 3, Bristol East ▬ Phase 4, Rocky Dale

The four phases

Phase 1: Pine Street

Done. Built August to November 2023.

Phase 2: Bristol West

Under construction since May 2026, projected to finish November 2027 · Nine streets west of North Street

Phase 3: Bristol East

In design. Bid in fall 2027, construction in 2028 · Main Street, East Street and five more streets

Phase 4: Rocky Dale

Planning. A short study of route options is recommended before design · Lines from the water tower across the mountain to Rocky Dale and to East Street

Shutoff notices, boil water notices and construction updates are posted on each phase’s page.

How the work is done

  • The old pipe stays in service during construction. In most places the new main is laid beside the old one. Once it is tested and approved, homes are switched over one at a time with only a short interruption. The old pipe is left in the ground.
  • Bigger pipe. Most new mains are larger than the old ones, which improves fire protection.
  • Service lines are replaced to the curb only if they are galvanized or lead.
  • Paving covers the trench where work took place.
  • Notice. The Town gives notice before planned water shutoffs and posts boil water notices on Front Porch Forum, Facebook and the phase pages.

Phase 1: Pine Street (completed 2023)

The 1905 water line under Pine Street was replaced from mid-August to mid-November 2023, after more than a decade of discussion. VTM Engineering finished the design, permits and bid documents after Green Mountain Engineering, which did the original study, closed in 2022. Munson Earth-Moving was chosen from seven bidders. The project finished under budget and ahead of schedule.

During the work, the Town found that the water line serving Lawson Lane had not been installed as its State permits required. Through negotiations the Town helped arrange, Munson connected the Lawson Lane homes to the new Pine Street main.

Phase pages

Bristol West (Phase 2)

Under construction. Shutoffs, boil water notices and updates.

Bristol East (Phase 3)

In design. Downtown plans and night work input.

Milestones

Oct 21, 2026

Bristol East design meeting

VTM Engineering presented the Main Street plan to downtown residents and businesses.

May 2026

Bristol West construction starts

Munson Earth Moving began work on the first streets.

Nov 5, 2024

Voters approve Phase 2 bond

Up to $3,950,000 for Bristol West.

2023

Phase 1 completed

Pine Street, under budget and ahead of schedule.

2022

Four-phase plan adopted

The full program was split into phases the State could finance.

2021

System study

Green Mountain Engineering’s study made the 1905 pipe a top priority.

Funding

Each phase is financed through the State’s Drinking Water State Revolving Fund, which can forgive part of the loan.

  • Phase 2, Bristol West: bond of up to $3,950,000 approved by voters in November 2024, with 50% loan forgiveness. Ratepayers repay about $2 million.
  • Phase 3, Bristol East: on the State’s 2026 list at an estimated $4,333,841 loan with about 50% forgiveness. It will need a voter-approved bond. Under the State’s current schedule, that vote would come by March 2027.

Phase 3 figures are State estimates.

Documents

Phase map, VTM Engineering

Image, September 2024

Bristol East presentation slides

PDF, October 21, 2026

Questions

Contact

Greg Faust, Town Administrator

Phone

(802) 453-2410 ext. 1

Engineer

VTM Engineering

Water operator

VTUMS

Thank you for your patience as we replace Bristol’s water infrastructure.

Boil water notice