Village-Wide Water Line Replacement
What
New water mains replacing 1905 cast iron
How
Four phases one done, one under way
Now
Phase 2 Bristol West, through Nov 2027
Next
Phase 3 Bristol East, 2028
Funding
50% forgiven State loans
Questions
Town Administrator (802) 453-2410 ext. 1
Why Bristol is replacing its water mains
More than half of Bristol’s water system went in around 1905. It is unlined cast iron pipe, well past its expected life. The old pipe leaks far more water than is typical, which raises operating costs and leads to emergency repairs, service interruptions and patched pavement. It also limits the water available to fight fires and raises the risk of contamination.
A 2021 engineering study of the whole system made replacing the 1905 pipe a top priority. The full job, then estimated at $12 to $13 million, was too large for the State to finance at once. In 2022 the Selectboard, acting as the Water Commission, split it into four phases.

▬ Phase 2, Bristol West ▬ Phase 3, Bristol East ▬ Phase 4, Rocky Dale
The four phases
Phase 1: Pine Street
Done. Built August to November 2023.
Under construction since May 2026, projected to finish November 2027 · Nine streets west of North Street
In design. Bid in fall 2027, construction in 2028 · Main Street, East Street and five more streets
Phase 4: Rocky Dale
Planning. A short study of route options is recommended before design · Lines from the water tower across the mountain to Rocky Dale and to East Street
Shutoff notices, boil water notices and construction updates are posted on each phase’s page.
How the work is done
- The old pipe stays in service during construction. In most places the new main is laid beside the old one. Once it is tested and approved, homes are switched over one at a time with only a short interruption. The old pipe is left in the ground.
- Bigger pipe. Most new mains are larger than the old ones, which improves fire protection.
- Service lines are replaced to the curb only if they are galvanized or lead.
- Paving covers the trench where work took place.
- Notice. The Town gives notice before planned water shutoffs and posts boil water notices on Front Porch Forum, Facebook and the phase pages.
Phase 1: Pine Street (completed 2023)
The 1905 water line under Pine Street was replaced from mid-August to mid-November 2023, after more than a decade of discussion. VTM Engineering finished the design, permits and bid documents after Green Mountain Engineering, which did the original study, closed in 2022. Munson Earth-Moving was chosen from seven bidders. The project finished under budget and ahead of schedule.
During the work, the Town found that the water line serving Lawson Lane had not been installed as its State permits required. Through negotiations the Town helped arrange, Munson connected the Lawson Lane homes to the new Pine Street main.
Phase pages
Under construction. Shutoffs, boil water notices and updates.
In design. Downtown plans and night work input.
Milestones
Oct 21, 2026
Bristol East design meeting
VTM Engineering presented the Main Street plan to downtown residents and businesses.
May 2026
Bristol West construction starts
Munson Earth Moving began work on the first streets.
Nov 5, 2024
Voters approve Phase 2 bond
Up to $3,950,000 for Bristol West.
2023
Phase 1 completed
Pine Street, under budget and ahead of schedule.
2022
Four-phase plan adopted
The full program was split into phases the State could finance.
2021
System study
Green Mountain Engineering’s study made the 1905 pipe a top priority.
Funding
Each phase is financed through the State’s Drinking Water State Revolving Fund, which can forgive part of the loan.
- Phase 2, Bristol West: bond of up to $3,950,000 approved by voters in November 2024, with 50% loan forgiveness. Ratepayers repay about $2 million.
- Phase 3, Bristol East: on the State’s 2026 list at an estimated $4,333,841 loan with about 50% forgiveness. It will need a voter-approved bond. Under the State’s current schedule, that vote would come by March 2027.
Phase 3 figures are State estimates.
Documents
Image, September 2024
Bristol West community meeting summary
PDF, May 6, 2026
Bristol East presentation slides
PDF, October 21, 2026
Questions
Contact
Greg Faust, Town Administrator
Phone
(802) 453-2410 ext. 1
Engineer
VTM Engineering
Water operator
VTUMS
Thank you for your patience as we replace Bristol’s water infrastructure.