Bristol West Waterline Project (Phase 2)
What
New water mains replacing 1905 cast iron
Where
Nine streets west of North Street
Boil water
None in effect as of November 17, 2026
Construction
2026 and 2027 two seasons
Funding
50% forgiven State loan
Questions
Town Administrator (802) 453-2410 ext. 1
Current status
November 17, 2026: No boil water notices are in effect. The last one, for Church Street and Pleasant Street, was lifted on November 17. Construction continues; notices about shutoffs and traffic are posted here and on the Town’s Front Porch Forum.
Updates and notices
| Date | Description | Documents | Video |
|---|---|---|---|
| November 17, 2026 | Bristol West Water: Church & Pleasant St Boil Lifted | Notice Memo_2026-11-17 | |
| November 16, 2026 | REVISED: Church Street and Pleasant Street Water Shutoff and Boil Water Notice, Monday, November 16 | Notice Memo_2026-11-16 | |
| November 13, 2026 | Church Street: Water Shutoff and Boil Water Notice, Monday, November 16 | Notice | |
| October 29, 2026 | Bristol West Water: Maple/Pleasant/Church Boil Lifted | Notice | |
| October 23, 2026 | Bristol West Water: Oct 26 Shut Off – North & Lawrence | Memo_2026-10-26 | |
| October 22, 2026 | Bristol West Water: Maple & West Boil Notice Remains On | Memo_2026-10-22 | |
| October 22, 2026 | Bristol West Water: Oct 22 Tie-In, West & Maple Traffic | Memo_2026-10-22 | |
| October 22, 2026 | Bristol West Water: Shut Off Oct 22 – Maple & Pleasant | Memo_2026-10-22 | |
| October 9, 2026 | Bristol West Water: Tie-In Oct 15, Pleasant & Maple Off | Memo_2026-10-15 | |
| September 4, 2026 | Bristol West Water: W Pleasant St Sept 8, Local Traffic | Memo_2026-09-08 | |
| August 13, 2026 | Maple Street: Water Work Moves South Toward West Street Next Week | Memo_2026-08-17 | |
| July 20, 2026 | Elm Street: Water Line Work Resumes This Week | Memo_2026-07-20 | |
| June 8, 2026 | Bristol West Water: Maple St Watermain Work, Local Only | Memo_2026-06-08 | |
| June 2, 2026 | Maple St June 3, Local Traffic Only | Memo_2026-06-02 | |
| May 29, 2026 | Taylor Avenue Work Continues June 1, Maple Street Next | Memo_2026-05-29 | |
| May 25, 2026 | Water System Construction on Elm Street | Memo_2026-05-25 | |
| May 6, 2026 | Bristol West Waterline Community Information Meeting | Summary | Video |
| September 23, 2024 | Selectboard Meeting | IV.3_Bristol_Water_Upgrade_District_Map_VTM_2024-09-18 IV.3 Bristol_West_Waterline_Replacement_Project_90%_Plans_VTM_2024-08 IV.3_Bristol_West_Opinion_of_Prob_Constr_Cost_VTM_2024-09-20 IV.3_Bristol_West_Opinion_of_Prob_Total_Project_Cost_VTM_2024-09-20 IV.3_E-mail_LEE_Re_Bristol_Water_Line_Soil_Borings_Plan_SMS#20245455_2024-09-18 IV.4_Bristol_West_Waterline_Replacement_Necessity_Resolution_2024-09-23_DRAFT IV.4_E-mails_Bond_Counsel_Re_Bristol_Bond_Vote_for_Nov. 5_deadlines_2024-09-20 IV.4_Bristol_West_Waterline_Replacement_Necessity_Resolution_2024-09-23_DRAFT_BPM_comments IV.5_Bristol_Special_Town_Meeting_Warning_2024-11-05_DRAFT | Video |
What is happening and why
Bristol is replacing its oldest water mains. Much of the system went in around 1905. It is unlined cast iron pipe, well past its expected life, and it leaks. That raises operating costs and leads to emergency repairs, service interruptions, lower fire flows and a higher risk of contamination.
The Town is doing the work in four phases: Phase 1 (Pine Street) is done. Phase 2, Bristol West, is under construction. Phase 3, Bristol East, is next. Phase 4 is Rocky Dale.
Phase 2 streets: Taylor Avenue, Elm Street, Maple Street, Pleasant Street, Church Street, Munsill Avenue, West Street, School Street and Park Street.
Munson Earth Moving Corporation is the contractor. VTM Engineering is the project engineer, and VTUMS is the Town’s water operator.

Blue: Phase 2, Bristol West · Red: Phase 3, Bristol East · Green: Phase 4, Rocky Dale
Timeline
| When | What |
|---|---|
| May 2026 | Construction started on the first streets. |
| November 2026 | Paving started. Streets finished in 2026 are paved this year. |
| Late winter or early spring 2027 | Public meeting with the contractor and a schedule, a month or two before work starts. |
| Starting about April 2027 | Proposed streets are West, Church, School and Park. The start depends on weather and frost. |
| End of October 2027 | Substantial completion, as projected by the contractor. |
| November 12, 2027 | Final completion, as projected by the contractor. |
As presented at the May 6, 2026 public meeting. Final schedule comes from the contractor. The spring 2027 meeting date is from the Oct 21, 2026 public meeting.
Spring 2027 work downtown
- April to June 2027. Work runs along the park, School Street and Park Street, then through the Main, North and West Street intersection to just past the traffic light.
- Done before July 1. The Selectboard set this deadline so summer events, the playground and downtown businesses are not in a work zone all summer.
- The intersection will not be dug up. A drill rig will bore the new pipe under it. A large stormwater pipe and fiber optic lines run through that intersection.
- Traffic: the goal is two-way traffic on West Street, with a possible lane shift.
- Walking: the goal is to keep the intersection open to people on foot.
- Equipment and access: the drill rig and other equipment will be set up near the intersection for a time. Part of the west entrance to Shaw’s, up by the drugstore, may be blocked. The engineer plans to share how long each area will be used.
- Night or day: some work in the middle of the road near the traffic light may happen at night. That will be decided this fall and winter.
- Exploratory digging: before connecting under the stormwater pipe, crews may dig for a day, possibly a Saturday, to see what is there.
As presented at the Oct 21, 2026 public meeting. Final schedule will come from the contractor.
What it means for you
- Work hours: normally 7 am to 5 pm. Crews may arrive earlier to ready equipment and may stay later to repair an unexpected break.
- Water shutoffs: water stays on except during tie-ins to existing mains or individual house connections. The Town gives notice before a planned shutoff.
- Unplanned interruptions: much of the old system was never well mapped, so crews can hit unmarked or damaged lines.
- Boil water notices: these may be issued when a line loses pressure while still in service.
- Driveways and parking: you should be able to get back to your driveway by the end of each work day. If you leave after crews arrive, park a little way down the road, outside the work zone.
- On the street: expect marking paint and flags, fencing, detours, blocked driveway entrances, street closures, noise, dust and traffic delays. Please leave the paint and flags in place and keep children away from work zones.
- Hydrants: some may be offline for a time. The fire department is told in advance and plans around it.
- Service lines: lines are replaced to the curb only if they are galvanized or lead.
- Paving: paving covers the trench area where work took place.
As presented at the May 6, 2026 public meeting.
Common questions
Will my water be shut off?
Possibly, for a tie-in or your house connection. Planned shutoffs come with advance notice.
Where do I get official updates?
This page, Front Porch Forum, and the Town’s Facebook and Instagram pages. To get updates by email, send your address to the Town Administrator.
Who do I contact with a problem during construction?
The Town Administrator’s Office. Please send concerns there rather than to the crews.
Funding
Voters approved a bond of up to $3,950,000 in November 2024. Financing comes through the State’s Drinking Water State Revolving Fund with 50% loan forgiveness.
Munson was the low bidder of nine at $2.42 million.
Source: May 6, 2026 community meeting summary.
Documents
- May 6 community meeting summary
- May 6 meeting recording
- Oct 21 meeting recording (spring 2027 work)
- Oct 21 presentation slides (West Street 2027 work)
- Bristol East (Phase 3) page
Questions
Greg Faust, Town Administrator
Town of Bristol, 1 South Street, P.O. Box 249, Bristol, VT 05443
(802) 453-2410 ext. 1
townadmin@bristolvt.org
Thank you for your patience as we replace Bristol’s water infrastructure.