Bristol West Waterline Project (Phase 2)

Bristol West Waterline Project (Phase 2)

What

New water mains replacing 1905 cast iron

Where

Nine streets west of North Street

Boil water

None in effect as of November 17, 2026

Construction

2026 and 2027 two seasons

Funding

50% forgiven State loan

Questions

Town Administrator (802) 453-2410 ext. 1

Current status

November 17, 2026: No boil water notices are in effect. The last one, for Church Street and Pleasant Street, was lifted on November 17. Construction continues; notices about shutoffs and traffic are posted here and on the Town’s Front Porch Forum.

Updates and notices

DateDescriptionDocumentsVideo
November 17, 2026Bristol West Water: Church & Pleasant St Boil LiftedNotice
Memo_2026-11-17
November 16, 2026REVISED: Church Street and Pleasant Street Water Shutoff and Boil Water Notice, Monday, November 16Notice
Memo_2026-11-16
November 13, 2026Church Street: Water Shutoff and Boil Water Notice, Monday, November 16Notice
October 29, 2026Bristol West Water: Maple/Pleasant/Church Boil LiftedNotice
October 23, 2026Bristol West Water: Oct 26 Shut Off – North & LawrenceMemo_2026-10-26
October 22, 2026Bristol West Water: Maple & West Boil Notice Remains OnMemo_2026-10-22
October 22, 2026Bristol West Water: Oct 22 Tie-In, West & Maple TrafficMemo_2026-10-22
October 22, 2026Bristol West Water: Shut Off Oct 22 – Maple & PleasantMemo_2026-10-22
October 9, 2026Bristol West Water: Tie-In Oct 15, Pleasant & Maple OffMemo_2026-10-15
September 4, 2026Bristol West Water: W Pleasant St Sept 8, Local TrafficMemo_2026-09-08
August 13, 2026Maple Street: Water Work Moves South Toward West Street Next
Week
Memo_2026-08-17
July 20, 2026Elm Street: Water Line Work Resumes This WeekMemo_2026-07-20
June 8, 2026Bristol West Water: Maple St Watermain Work, Local OnlyMemo_2026-06-08
June 2, 2026Maple St June 3, Local Traffic OnlyMemo_2026-06-02
May 29, 2026Taylor Avenue Work Continues June 1, Maple Street NextMemo_2026-05-29
May 25, 2026Water System Construction on Elm StreetMemo_2026-05-25
May 6, 2026Bristol West Waterline Community Information MeetingSummaryVideo
September 23, 2024Selectboard MeetingIV.3_Bristol_Water_Upgrade_District_Map_VTM_2024-09-18
IV.3 Bristol_West_Waterline_Replacement_Project_90%_Plans_VTM_2024-08
IV.3_Bristol_West_Opinion_of_Prob_Constr_Cost_VTM_2024-09-20
IV.3_Bristol_West_Opinion_of_Prob_Total_Project_Cost_VTM_2024-09-20
IV.3_E-mail_LEE_Re_Bristol_Water_Line_Soil_Borings_Plan_SMS#20245455_2024-09-18
IV.4_Bristol_West_Waterline_Replacement_Necessity_Resolution_2024-09-23_DRAFT
IV.4_E-mails_Bond_Counsel_Re_Bristol_Bond_Vote_for_Nov. 5_deadlines_2024-09-20
IV.4_Bristol_West_Waterline_Replacement_Necessity_Resolution_2024-09-23_DRAFT_BPM_comments
IV.5_Bristol_Special_Town_Meeting_Warning_2024-11-05_DRAFT
Video

What is happening and why

Bristol is replacing its oldest water mains. Much of the system went in around 1905. It is unlined cast iron pipe, well past its expected life, and it leaks. That raises operating costs and leads to emergency repairs, service interruptions, lower fire flows and a higher risk of contamination.

The Town is doing the work in four phases: Phase 1 (Pine Street) is done. Phase 2, Bristol West, is under construction. Phase 3, Bristol East, is next. Phase 4 is Rocky Dale.

Phase 2 streets: Taylor Avenue, Elm Street, Maple Street, Pleasant Street, Church Street, Munsill Avenue, West Street, School Street and Park Street.

Munson Earth Moving Corporation is the contractor. VTM Engineering is the project engineer, and VTUMS is the Town’s water operator.

Map of the Bristol village water system. Phase 2 streets are blue, Phase 3 streets are red and Phase 4 is green.
VTM Engineering phase map, September 2024. Preliminary, not for construction.

Blue: Phase 2, Bristol West · Red: Phase 3, Bristol East · Green: Phase 4, Rocky Dale

Timeline

WhenWhat
May 2026Construction started on the first streets.
November 2026Paving started. Streets finished in 2026 are paved this year.
Late winter or early spring 2027Public meeting with the contractor and a schedule, a month or two before work starts.
Starting about April 2027Proposed streets are West, Church, School and Park. The start depends on weather and frost.
End of October 2027Substantial completion, as projected by the contractor.
November 12, 2027Final completion, as projected by the contractor.

As presented at the May 6, 2026 public meeting. Final schedule comes from the contractor. The spring 2027 meeting date is from the Oct 21, 2026 public meeting.

Spring 2027 work downtown

  • April to June 2027. Work runs along the park, School Street and Park Street, then through the Main, North and West Street intersection to just past the traffic light.
  • Done before July 1. The Selectboard set this deadline so summer events, the playground and downtown businesses are not in a work zone all summer.
  • The intersection will not be dug up. A drill rig will bore the new pipe under it. A large stormwater pipe and fiber optic lines run through that intersection.
  • Traffic: the goal is two-way traffic on West Street, with a possible lane shift.
  • Walking: the goal is to keep the intersection open to people on foot.
  • Equipment and access: the drill rig and other equipment will be set up near the intersection for a time. Part of the west entrance to Shaw’s, up by the drugstore, may be blocked. The engineer plans to share how long each area will be used.
  • Night or day: some work in the middle of the road near the traffic light may happen at night. That will be decided this fall and winter.
  • Exploratory digging: before connecting under the stormwater pipe, crews may dig for a day, possibly a Saturday, to see what is there.

As presented at the Oct 21, 2026 public meeting. Final schedule will come from the contractor.

What it means for you

  • Work hours: normally 7 am to 5 pm. Crews may arrive earlier to ready equipment and may stay later to repair an unexpected break.
  • Water shutoffs: water stays on except during tie-ins to existing mains or individual house connections. The Town gives notice before a planned shutoff.
  • Unplanned interruptions: much of the old system was never well mapped, so crews can hit unmarked or damaged lines.
  • Boil water notices: these may be issued when a line loses pressure while still in service.
  • Driveways and parking: you should be able to get back to your driveway by the end of each work day. If you leave after crews arrive, park a little way down the road, outside the work zone.
  • On the street: expect marking paint and flags, fencing, detours, blocked driveway entrances, street closures, noise, dust and traffic delays. Please leave the paint and flags in place and keep children away from work zones.
  • Hydrants: some may be offline for a time. The fire department is told in advance and plans around it.
  • Service lines: lines are replaced to the curb only if they are galvanized or lead.
  • Paving: paving covers the trench area where work took place.

As presented at the May 6, 2026 public meeting.

Common questions

Will my water be shut off?
Possibly, for a tie-in or your house connection. Planned shutoffs come with advance notice.

Where do I get official updates?
This page, Front Porch Forum, and the Town’s Facebook and Instagram pages. To get updates by email, send your address to the Town Administrator.

Who do I contact with a problem during construction?
The Town Administrator’s Office. Please send concerns there rather than to the crews.

Funding

Voters approved a bond of up to $3,950,000 in November 2024. Financing comes through the State’s Drinking Water State Revolving Fund with 50% loan forgiveness.

Munson was the low bidder of nine at $2.42 million.

Source: May 6, 2026 community meeting summary.

Questions

Greg Faust, Town Administrator
Town of Bristol, 1 South Street, P.O. Box 249, Bristol, VT 05443
(802) 453-2410 ext. 1
townadmin@bristolvt.org

Thank you for your patience as we replace Bristol’s water infrastructure.